Texas Property Code indicates that a lien release should be filed with the County Property Records Office after the claim has been paid and no later than ten (10) days after the written request has been received. In other words, time does not start until the request to release a lien has been sent to the contractor/supplier in writing.
You must also make sure all the checks given to you have been cleared and the debt is 100% satisfied before signing the lien release.
Related questions and answers
Texas Property Code indicates that a lien release should be filed with the County Property Records Office after the claim has been paid and no later than ten (10) days after the written request has been received. In other words, time does not start until the request to release a lien has been sent to the contractor/supplier in writing. You must also make sure all the checks given to you have been cleared and the debt is 100% satisfied before signing the lien release.
All lien affidavits (construction liens), Sworn Statement of Accounts (document attached to a bond claim), and lien releases must be notarized and filed. Bond Claim Sworn Statement of Accounts are filed with the Surety Company on record, and they should be mailed via Certified Mail with Return Receipt Requested.
The county appraisal district websites are free and can provide you with the project owner’s name, mailing address, and legal description of the property. Make sure to search the real property records and not the business/personal property records. To locate a county appraisal district website search online by typing (county name) Texas tax appraisal district website. For example: “Harris County, Texas, tax appraisal district website” or “Harris CAD.” Then select their “Property Search” link and enter owner’s name and/or street address to search for property information. Make sure you have identified the correct legal name of the owner of the property, it could also be a company name. Finding property information in the tax appraisal websites is sometimes difficult and although having the legal description in the lien documents is preferred, if you know the actual street address of the project, you may use that instead and your lien will still be valid.
No. Texas Easy Lien system is currently designed to prepare lien and bond documents for commercial and Texas government public projects.
The dates and deadlines related for lien claims are based off the month and year in which the work was actually performed. The invoice date and company accounting methods are irrelevant in these cases.
Additionally, to qualify to file a lien claim on a property for a commercial project, the subcontractor or supplier, is required to send the invoice or request payment by the 15th day of the second month after the month the work was performed.
A subcontractor who has a direct contract with the General Contractor is called a Tier 1 Subcontractor. The chart below shows the deadline to send Invoices, Pre-lien Notice Letter and Lien Affidavit for private commercial projects for Tier 1 Subcontractors:
FOR CLAIMS RESULTING FROM A CONTRACT SIGNED BEFORE DECEMBER 31ST, 2021
IF THE 15th OF THE MONTH FALLS ON A WEEKEND OR A HOLIDAY, THE LAST DAY TO FILE A VALID LIEN WILL BE THE EARLIEST BUSINESS DAY.
FOR CLAIMS RESULTING FROM A CONTRACT SIGNED AFTER JANUARY 1ST, 2022
IF THE 15th OF THE MONTH FALLS ON A WEEKEND OR A HOLIDAY, THE LAST DAY TO FILE A VALID LIEN WILL EXTEND TO THE NEXT BUSINESS DAY AFTER THAT WEEKEND OR HOLIDAY.
Original (General) Contractor - Constitutional - Mechanic’s Lien Requirements | |||
---|---|---|---|
Chart of Filing Deadlines | |||
Month of: a) Written Termination b) Abandonment of Project c) Settlement or: d) Completion of the Contract | Commercial Projects (Private) 🔗 | ||
Pre-lien Notice to Property Owner is Not Required |
File the Lien Affidavit On or Before: | ||
January | None | May 15th | |
February | None | June 15th | |
March | None | July 15th | |
April | None | August 15th | |
May | None | September 15th | |
June | None | October 15th | |
July | None | November 15th | |
August | None | December 15th | |
September | None | January 15th | |
October | None | February 15th | |
November | None | March 15th | |
December | None | April 15th |
Subcontractor (1st Tier) Lien Requirements | |||
---|---|---|---|
Chart of Filing Deadlines | |||
Month of Activity | Commercial Projects (Private) 🔗 | ||
Send Invoice by: | Send Pre-lien Notice to Property Owner and Original Contractor by: |
File the lien by the following date OR within 30 days after the overall project is complete**. | |
January | March 15th | April 15th | May 15th |
February | April 15th | May 15th | June 15th |
March | May 15th | June 15th | July 15th |
April | June 15th | July 15th | August 15th |
May | July 15th | August 15th | September 15th |
June | August 15th | September 15th | October 15th |
July | September 15th | October 15th | November 15th |
August | October 15th | November 15th | December 15th |
September | November 15th | December 15th | January 15th |
October | December 15th | January 15th | February 15th |
November | January 15th | February 15th | March 15th |
December | February 15th | March 15th | April 15th |
IMPORTANT:
**You can file a lien affidavit 30 days after completing the overall project only if you sent the pre-lien notice for that specific month on time.
|
Sub-subcontractor (2nd Tier) Lien Requirements | |||
---|---|---|---|
Chart of Filing Deadlines | |||
Month of Activity | Commercial Projects (Private) 🔗 | ||
Send Invoice by: | Send Pre-lien Notice to Property Owner and Original Contractor by: |
File the lien by the following date OR within 30 days after the overall project is complete**. | |
January | March 15th | April 15th | May 15th |
February | April 15th | May 15th | June 15th |
March | May 15th | June 15th | July 15th |
April | June 15th | July 15th | August 15th |
May | July 15th | August 15th | September 15th |
June | August 15th | September 15th | October 15th |
July | September 15th | October 15th | November 15th |
August | October 15th | November 15th | December 15th |
September | November 15th | December 15th | January 15th |
October | December 15th | January 15th | February 15th |
November | January 15th | February 15th | March 15th |
December | February 15th | March 15th | April 15th |
IMPORTANT:
**You can file a lien affidavit 30 days after completing the overall project only if you sent the pre-lien notice for that specific month on time.
|