Do I have to send a Pre-lien Notice Letter if I am the general (prime) contractor?

No. Only subcontractors, sub-subcontractors and suppliers who do not have a direct contract with the project owner are required to send a Pre-lien Notice Letter (for each month that is unpaid) before filing a mechanic’s lien affidavit with the county.

What should I do if the contract is with someone who is renting or leasing the property?

The project owner is who hired the general contractor and/or subcontractors to perform labor or services to a construction or repair project. If this person or company does not own the property but is only leasing or renting it, this is still the person you must list as the project owner. However, the real owner of the property should also receive copies of all documents since the lien will be attached to this person’s property.

If a certain month did not qualify, did I lose my lien rights on the project?

If you missed the deadline to send a notice or file a lien claim for one specific month and you are still owed for more months after that, you may still qualify to file a lien claim. The deadline chart above will assist in guiding you through each month’s deadlines.