Currently, Texas Easy Lien provides help preparing bond claim documents only for State Public Projects. If you are owed in a construction project that is owned by a Federal Entity, we suggest you immediately consult with your lawyer to assert your rights.
Related questions and answers
The dates and deadlines related for lien claims are based off the month and year in which the work was actually performed. The invoice date and company accounting methods are irrelevant in these cases.
Additionally, to qualify to file a lien claim on a property for a commercial project, the subcontractor or supplier, is required to send the invoice or request payment by the 15th day of the second month after the month the work was performed.
A subcontractor who has a direct contract with the General Contractor is called a Tier 1 Subcontractor. The chart below shows the deadline to send Invoices, Pre-lien Notice Letter and Lien Affidavit for private commercial projects for Tier 1 Subcontractors:
FOR CLAIMS RESULTING FROM A CONTRACT SIGNED BEFORE DECEMBER 31ST, 2021
IF THE 15th OF THE MONTH FALLS ON A WEEKEND OR A HOLIDAY, THE LAST DAY TO FILE A VALID LIEN WILL BE THE EARLIEST BUSINESS DAY.
FOR CLAIMS RESULTING FROM A CONTRACT SIGNED AFTER JANUARY 1ST, 2022
IF THE 15th OF THE MONTH FALLS ON A WEEKEND OR A HOLIDAY, THE LAST DAY TO FILE A VALID LIEN WILL EXTEND TO THE NEXT BUSINESS DAY AFTER THAT WEEKEND OR HOLIDAY.
Original (General) Contractor - Constitutional - Mechanic’s Lien Requirements | |||
---|---|---|---|
Chart of Filing Deadlines | |||
Month of: a) Written Termination b) Abandonment of Project c) Settlement or: d) Completion of the Contract | Commercial Projects (Private) 🔗 | ||
Pre-lien Notice to Property Owner is Not Required |
File the Lien Affidavit On or Before: | ||
January | None | May 15th | |
February | None | June 15th | |
March | None | July 15th | |
April | None | August 15th | |
May | None | September 15th | |
June | None | October 15th | |
July | None | November 15th | |
August | None | December 15th | |
September | None | January 15th | |
October | None | February 15th | |
November | None | March 15th | |
December | None | April 15th |
Subcontractor (1st Tier) Lien Requirements | |||
---|---|---|---|
Chart of Filing Deadlines | |||
Month of Activity | Commercial Projects (Private) 🔗 | ||
Send Invoice by: | Send Pre-lien Notice to Property Owner and Original Contractor by: |
File the lien by the following date OR within 30 days after the overall project is complete**. | |
January | March 15th | April 15th | May 15th |
February | April 15th | May 15th | June 15th |
March | May 15th | June 15th | July 15th |
April | June 15th | July 15th | August 15th |
May | July 15th | August 15th | September 15th |
June | August 15th | September 15th | October 15th |
July | September 15th | October 15th | November 15th |
August | October 15th | November 15th | December 15th |
September | November 15th | December 15th | January 15th |
October | December 15th | January 15th | February 15th |
November | January 15th | February 15th | March 15th |
December | February 15th | March 15th | April 15th |
IMPORTANT:
**You can file a lien affidavit 30 days after completing the overall project only if you sent the pre-lien notice for that specific month on time.
|
Sub-subcontractor (2nd Tier) Lien Requirements | |||
---|---|---|---|
Chart of Filing Deadlines | |||
Month of Activity | Commercial Projects (Private) 🔗 | ||
Send Invoice by: | Send Pre-lien Notice to Property Owner and Original Contractor by: |
File the lien by the following date OR within 30 days after the overall project is complete**. | |
January | March 15th | April 15th | May 15th |
February | April 15th | May 15th | June 15th |
March | May 15th | June 15th | July 15th |
April | June 15th | July 15th | August 15th |
May | July 15th | August 15th | September 15th |
June | August 15th | September 15th | October 15th |
July | September 15th | October 15th | November 15th |
August | October 15th | November 15th | December 15th |
September | November 15th | December 15th | January 15th |
October | December 15th | January 15th | February 15th |
November | January 15th | February 15th | March 15th |
December | February 15th | March 15th | April 15th |
IMPORTANT:
**You can file a lien affidavit 30 days after completing the overall project only if you sent the pre-lien notice for that specific month on time.
|
Texas Property Code Chapter 53 states that only those who are filing a lien as landscapers, landscape materials supplier, demolition service providers and professional designers must have a written contract with the owner or the owner’s agent. However, it does not provide an exemption for them to file as contractors or any other subcontractor or supplier.
Condominiums and spec homes are only residential construction projects if they have been purchased by the person owner who is going to occupy them live there before the beginning of construction. In other words, if the owner of a lot hires a contractor to build a house but is not going to live there, then it is considered to be a commercial construction project. But if the owner of the lot will actually live in the house under construction, then it is considered to be a residential construction project.
If you have been paid for the month you filed a lien on a property and you received the request to release the lien, then you should sign a lien release. However, if you are still owed for more months and filed a lien(s) for them as well, those liens should remain in place until the balance gets paid.
The project owner is who hired the general contractor and/or subcontractors to perform labor or services to a construction or repair project. If this person or company does not own the property but is only leasing or renting it, this is still the person you must list as the project owner. However, the real owner of the property should also receive copies of all documents since the lien will be attached to this person’s property.