Texas Property Code indicates that a lien release should be filed with the County Property Records Office after the claim has been paid and no later than ten (10) days after the written request has been received. In other words, time does not start until the request to release a lien has been sent to the contractor/supplier in writing.
You must also make sure all the checks given to you have been cleared and the debt is 100% satisfied before signing the lien release.
Related questions and answers
This is an important issue that is often misunderstood. The dates and deadlines related for lien and bond claims are based off the month and year in which the work was actually performed. The invoice date and company accounting methods are irrelevant for these claims. The important issues are when the work was actually performed and the value of the work for each individual month. A helpful example? Assume that a contractor completed a three-month painting project that lasted from January to March. The contractor would need to separately identify the value of the work performed for January, February, and March. It would not matter if only one invoice was issued at the end of the project. The deadlines will vary depending on the type of document and the type of contractor or supplier. General deadlines can be found in the chart below.
FOR CLAIMS RESULTING FROM A CONTRACT SIGNED BEFORE DECEMBER 31ST, 2021
IF THE 15th OF THE MONTH FALLS ON A WEEKEND OR A HOLIDAY, THE LAST DAY TO FILE A VALID LIEN WILL BE THE EARLIEST BUSINESS DAY.
FOR CLAIMS RESULTING FROM A CONTRACT SIGNED AFTER JANUARY 1ST, 2022
IF THE 15th OF THE MONTH FALLS ON A WEEKEND OR A HOLIDAY, THE LAST DAY TO FILE A VALID LIEN WILL EXTEND TO THE NEXT BUSINESS DAY AFTER THAT WEEKEND OR HOLIDAY.
Original (General) Contractor - Constitutional - Mechanic’s Lien Requirements | |||
---|---|---|---|
Chart of Filing Deadlines | |||
Month of: a) Written Termination b) Abandonment of Project c) Settlement or: d) Completion of the Contract | Commercial Projects (Private) 🔗 | ||
Pre-lien Notice to Property Owner is Not Required |
File the Lien Affidavit On or Before: | ||
January | None | May 15th | |
February | None | June 15th | |
March | None | July 15th | |
April | None | August 15th | |
May | None | September 15th | |
June | None | October 15th | |
July | None | November 15th | |
August | None | December 15th | |
September | None | January 15th | |
October | None | February 15th | |
November | None | March 15th | |
December | None | April 15th |
Subcontractor (1st Tier) Lien Requirements | |||
---|---|---|---|
Chart of Filing Deadlines | |||
Month of Activity | Commercial Projects (Private) 🔗 | ||
Send Invoice by: | Send Pre-lien Notice to Property Owner and Original Contractor by: |
File the lien by the following date OR within 30 days after the overall project is complete**. | |
January | March 15th | April 15th | May 15th |
February | April 15th | May 15th | June 15th |
March | May 15th | June 15th | July 15th |
April | June 15th | July 15th | August 15th |
May | July 15th | August 15th | September 15th |
June | August 15th | September 15th | October 15th |
July | September 15th | October 15th | November 15th |
August | October 15th | November 15th | December 15th |
September | November 15th | December 15th | January 15th |
October | December 15th | January 15th | February 15th |
November | January 15th | February 15th | March 15th |
December | February 15th | March 15th | April 15th |
IMPORTANT:
**You can file a lien affidavit 30 days after completing the overall project only if you sent the pre-lien notice for that specific month on time.
|
Sub-subcontractor (2nd Tier) Lien Requirements | |||
---|---|---|---|
Chart of Filing Deadlines | |||
Month of Activity | Commercial Projects (Private) 🔗 | ||
Send Invoice by: | Send Pre-lien Notice to Property Owner and Original Contractor by: |
File the lien by the following date OR within 30 days after the overall project is complete**. | |
January | March 15th | April 15th | May 15th |
February | April 15th | May 15th | June 15th |
March | May 15th | June 15th | July 15th |
April | June 15th | July 15th | August 15th |
May | July 15th | August 15th | September 15th |
June | August 15th | September 15th | October 15th |
July | September 15th | October 15th | November 15th |
August | October 15th | November 15th | December 15th |
September | November 15th | December 15th | January 15th |
October | December 15th | January 15th | February 15th |
November | January 15th | February 15th | March 15th |
December | February 15th | March 15th | April 15th |
IMPORTANT:
**You can file a lien affidavit 30 days after completing the overall project only if you sent the pre-lien notice for that specific month on time.
|
Nothing. Texas Easy Lien will have access to your documents once they are notarized, and we will file them with the county for you.
The project owner is who hired the general contractor and/or subcontractors to perform labor or services to a construction or repair project. If this person or company does not own the property but is only leasing or renting it, this is still the person you must list as the project owner. However, the real owner of the property should also receive copies of all documents since the lien will be attached to this person’s property.
The lien release should be signed and notarized by the same person (contractor) who filed the mechanic’s lien. Preparing and filing the document itself can be done by the interested party (i.e. the project owner) or any other individual.
To prepare a lien affidavit, you will need the general information of the project and your contract. Below is a list of most of the information that is most needed to file a lien. • Project Information: Owner, name of project, common address (or legal property description), county where the project is located. • For Subcontractors: Name (or company name) and mailing address of the General (Prime) Contractor. • For Sub-subcontractors: It is not required but preferred to have the name and mailing address of all Subcontractors involved in the contract chain. • Work: Invoice dates, description of the unpaid work performed and the amount owed per each individual month.